Mälarenergi AB is planning to invest in a new combined heat and power (CHP) plant with auxiliary systems and to modernise the existing plant in Västerås. The Project consists of four main parts: A steam boiler of 150 MWth for combustion of recycled wood fuel; A back-pressure steam turbine of about 55 MWe; A flue gas treatment system including flue gas condensation and combustion air moisturising system with condensate cleaning; A fuel handling system to supply the boiler with fuel. This procurement (Dnr 2015/34) relates to steam turbine.
Sista ansökningsdag
Tidsfristen för mottagande av anbud var 2015-08-31.
Upphandlingen offentliggjordes den 2015-07-08.
Vem?
Vad?
Var?
Upphandlingshistorik
Datum |
Dokument |
2015-07-08
|
Meddelande om upphandling
|