SN01 Värtan

Ellevio AB

Ellevios substation Värtan, in the following named Sn01, in Stockholm, is to be renewed. Additional capacity, meaning increased numbers of bays at both 110 kV and 220 kV levels, will support the growth and future expansion of Stockholm. Besides 110 kV and 220 kV, which is the main part, the substation also includes a small part 33 kV.
A new building with a completely new electrical substation is in the scope, in addition to the construction of new underground cable connections, in ground and in concrete troughs to the substation.
The new Sn01 will be built, using GIS-technology, on the existing substation premises.