A turnkey contract regarding a 6 MW boiler fuelled by wooden pellets. The pellets could also be of industrial quality. The boiler will be fitted into an existing building. The boiler will work as a single production unit as well as a unit together with other boilers in the same plant and even in the complete district heating system. The boiler should be built to meet the requirements as a 72h periodic monitoring (AFS2002:1(§17 och § 18)).
The boiler shall be equipped with an industrial control system which should be able to connect to a parenting system.
The boiler shall be built as a hot water boiler (110 °C) and have construction pressure on the boiler PN10/150 °C.
Requirements regarding combustion properties.
Environmental value, NOX (10 min. mean) 50 mg/MJ.
Environmental value, CO (10 min. mean).
120 mg/MJ.
Environmental value, Dust (ndg vid 13 % CO2) (10 min. mean) 20 mg/m3ndg.
Sista ansökningsdag
Tidsfristen för mottagande av anbud var 2015-05-04.
Upphandlingen offentliggjordes den 2015-04-02.
Vem?
Vad?
Var?
Upphandlingshistorik
Datum |
Dokument |
2015-04-02
|
Meddelande om upphandling
|
2015-04-10
|
Ytterligare upplysningar
|
2015-05-04
|
Ytterligare upplysningar
|