Upphandlingar: Hjälpapparater för användning tillsammans med ånggeneratorer

7 arkiverade upphandlingar

Hjälpapparater för användning tillsammans med ånggeneratorer har anskaffats av organisationer som t.ex Mälarenergi AB och Stockholm Exergi AB.

Nyligen genomförda upphandlingar av hjälpapparater för användning tillsammans med ånggeneratorer i Sverige

2019-09-23   SNCR (Selective Non-Catalytic Reduction) for KVV1 in Värtan, Stockholm (Stockholm Exergi AB)
Stockholm Exergi is the energy company of Stockholm, owned by the City of Stockholm and Fortum. Stockholm Exergi plans to extend the operational life of 1 of the boilers including auxiliary equipment at Värtaverket. The boiler KVV1 has a heat output of over 300 MW, but also a significant electricity production. The boiler was commissioned in 1976 and a prolongation of life for 25 years is planned. This includes switching to biofuel. The plant needs to be overhauled and major parts need to be replaced or … Visa upphandlingen »
2019-09-17   Boiler Cleaning System for KVV1 in Värtan, Stockholm (Stockholm Exergi AB)
Stockholm Exergi is the energy company of Stockholm, owned by the City of Stockholm and Fortum. Stockholm Exergi plans to extend the operational life of one of the boilers at Värtaverket in the city, KVV1, including switching to biofuel. The boiler KVV1 has a heat output of over 300 MW, but also a significant electricity production. In order to renew the cleaning system of the boiler, the plan is to replace existing sootblowers, install additional sootblowers and other soot cleaning equipment in selected … Visa upphandlingen »
2016-10-10   Fuel handling system (Mälarenergi AB)
Mälarenergi AB is planning to invest in a new combined heat and power (CHP) plant with auxiliary systems and to modernise the existing plant in Västerås. The Project consists of 4 main parts: A steam boiler of 150 — 180 MWth for combustion of recycled wood fuel, a district heating condensing steam turbine of about 55 — 65 MWe, a flue gas treatment system and a fuel handling system including preparation and storage to supply the boiler with solid fuel. This procurement (Dnr 2016/44) relates to the … Visa upphandlingen »
2015-07-08   Fuel handling system (Mälarenergi AB)
Mälarenergi AB is planning to invest in a new combined heat and power (CHP) plant with auxiliary systems and to modernise the existing plant in Västerås. The project consists of 4 main parts: A steam boiler of 150 MWth for combustion of recycled wood fuel; A back-pressure steam turbine of about 55 MWe; A flue gas treatment system including flue gas condensation and combustion air moisturizing system with condensate cleaning; A fuel handling system to supply the boiler with fuel. This procurement (Dnr … Visa upphandlingen »
2011-06-30   2011.20 fuel preparation plant (Mälarenergi AB)
Mälarenergi AB, Västerås, Sweden invites to tender application regarding the purchase of a fuel preparation plant for the production of solid recovered fuel (SRF). Visa upphandlingen »
2011-04-08   2011.18 Invitation to tender application flue gas cleaning (Mälarenergi AB)
Mälarenergi AB, Västerås, Sweden invites to tender application regarding the purchase of a system for flue gas cleaning including flue gas condensation and condensate cleaning. Visa upphandlingen »
2011-04-08   2011.18 Invitation to tender application Flue Gas Cleaning (Mälarenergi AB)
Mälarenergi AB, Västerås, Sweden invites to tender application regarding the purchase of a system for Flue gas cleaning including flue gas condensation and condensate cleaning. Visa upphandlingen »