New transport (conveyor) system for bottom ash, boiler 6 in Högdalen

AB Fortum Värme samägt med Stockholms stad

Rebuild of bottom ash system for 91 MW CFB boiler with industrial waste as the primary fuel. The scope includes a new conveying system for transportation of the bottom ash from the boiler to the slag bunker. It also includes recirculation of fine fractions bottom ash to the furnance. It is of utmost importance that the proposed solution complies to the operation of the boiler. The complete process has to be taken into account, e.g. sand consumption, dust, temperatures, work environment and maintainability etc. The supplier need to give a functional guarantee for the scope.

Sista ansökningsdag
Tidsfristen för mottagande av anbud var 2011-09-01. Upphandlingen offentliggjordes den 2011-07-01.

Vem?

Vad?

Var?

Upphandlingshistorik
Datum Dokument
2011-07-01 Meddelande om upphandling