The biomass power plant KVV8 at Värtaverket, Stockholm, Sweden, receives biomass by train up to several times a day all days a week. Each train set has 23 to 32 wagons and there are 2 or 3 containers with biomass on each wagon. Each container contain around 50 m of biofuel. The unloading of the biomass is done by an unloading robot which empties each container on the train into a fuel pit. This project aims to take representative samples of the biomass in each container before they are emptied within the fuel pit.
Preliminary time schedule:
Installation completed and the sampling equipment ready for commissioning in mid-August 2019.
Sista ansökningsdag
Tidsfristen för mottagande av anbud var 2018-09-18.
Upphandlingen offentliggjordes den 2018-09-03.
Objekt Upphandlingens omfattning
Titel: Biomass Sampling KVV8 Värtaverket Stockholm — Train
UH-2018-118
Produkter/tjänster: Fuktmätare📦
Kort beskrivning:
“The biomass power plant KVV8 at Värtaverket, Stockholm, Sweden, receives biomass by train up to several times a day all days a week. Each train set has 23...”
Kort beskrivning
The biomass power plant KVV8 at Värtaverket, Stockholm, Sweden, receives biomass by train up to several times a day all days a week. Each train set has 23 to 32 wagons and there are 2 or 3 containers with biomass on each wagon. Each container contain around 50 m of biofuel. The unloading of the biomass is done by an unloading robot which empties each container on the train into a fuel pit. This project aims to take representative samples of the biomass in each container before they are emptied within the fuel pit.
Preliminary time schedule:
Installation completed and the sampling equipment ready for commissioning in mid-August 2019.
1️⃣
Ytterligare produkter/tjänster: Fuktighetsmätare📦
Ytterligare produkter/tjänster: Fuktmätare📦
Ytterligare produkter/tjänster: Bränslen📦
Ytterligare produkter/tjänster: Industriinspektion📦
Plats för genomförandet: Stockholm🏙️
Huvudort eller plats för utförandet: Värtaverket
Beskrivning av upphandlingen:
“The biomass power plant KVV8 at Värtaverket, Stockholm, Sweden, receives biomass by train up to several times a day all days a week. Each train set has 23...”
Beskrivning av upphandlingen
The biomass power plant KVV8 at Värtaverket, Stockholm, Sweden, receives biomass by train up to several times a day all days a week. Each train set has 23 to 32 wagons and there are 2 or 3 containers with biomass on each wagon. Each container contain around 50 m of biofuel. The unloading of the biomass is done by an unloading robot which empties each container on the train into a fuel pit. This project aims to take representative samples of the biomass in each container before they are emptied within the fuel pit.
Preliminary time schedule:
Installation completed and the sampling equipment ready for commissioning in mid-August 2019.
Visa mer Kriterier för tilldelning
Priset är inte det enda tilldelningskriteriet och alla kriterier anges endast i upphandlingsdokumenten
Varaktighet
Startdatum: 2018-10-26 📅
Slutdatum: 2021-10-26 📅
Information om alternativen
Alternativ ✅
Beskrivning av alternativen: Complementary equipment
Förfarande Typ av förfarande
Förhandlat förfarande med föregående konkurrensutsättning
Administrativ information
Tidsfrist för mottagande av anbud eller begäran om deltagande: 2018-09-18 📅
Språk på vilka anbud eller ansökningar om deltagande kan lämnas in: engelska 🗣️
Språk på vilka anbud eller ansökningar om deltagande kan lämnas in: svenska 🗣️
Anbudet skall vara giltigt till och med: 2018-12-10 📅